St James Court, Kirk Road is a development in an established residential area in the village of Church near Accrington, offering picturesque countryside views and adjacent to the Leeds-Liverpool Canal.
HA Groundworks were proud to be appointed as a contractor to undertake the relevant preparation works for the final surfacing and adoption by the Local Authority.
Our works were completed in a efficient and timely manner with regular interaction with the local residents to ensure minimal disruption throughout the ‘live’ development.
Duration of Works | 8 weeks |
New Kerbs | 259m |
Iron Works | 61 Nr |
Surfacing | 2,775.66m2 |
Good feedback was received from the residents within the development during the course of our works.
The residents of Kirk Road